19th May 2026
Agenda
Action items from the last call - Bosko
Node 11.0.1 & DBSync 13.7.0.5 - Sam/Ramsay/Jeff
Van Rossem Upgrade Update - Bosko, all
Ogmios PR
Can it be done so its van Rossem ready instead of Dijkstra ready?
How would Dijkstra features be enabled later?
van Rossem hard fork progress - Bosko
PreProd
Are we ready to vote, ratify and enact hf ga on preprod? (first next possible enactment date is 26st May if its voted for until 21st May - epoch boundary on PreProd)
Mainnet
Are we on the track to submit it on 29th May?
Plutus Cost Model - Kevin, Ryan, Bosko
PreProd - submitted, ratified, was enacted at the epoch boundary on 16th May
Mainnet
van Rossem comms - Ian / Larisa
Comms plan - CF, Midnight, Shielded, Emurgo, Intersect, IO
Weekly comms meeting
Comms in the last week - anything we missed
Comms in the week ahead
AOB
Key materials
Summary
Ogmios and Kupo readiness continues to be the biggest challenge for the hard fork progress
Ogmios should be added to the critical tooling list
It should be pointed out in any comms mentioning that Ogmios isnt ready yet, that its the private project
Main issue from the Ogmios team perspective is that the impact is big due to the fact that the node version 11.0.1, which is meant for van Rossem, also contains some feature of the future hard fork/era Dijkstra
IO team members John and Erik created massive PRs in draft trying to unblock progress even though its not their codebase
Matthias from the Ogmios team is participating as much as possible giving his guidance, reviews and technical expertise but time availability continues to be the issue
There are at least two possible approaches
Continue to work on the PRs in their current state trying to get them over the line and in the position to be merged or
Create PRs with the reduced scope to focus on the van Rossem readiness support and keeing Dijkstra features support as little as needed
It was decided that IO team should try to get additional resources in reviewing the work being done by John and Erik and giving it potentially the last needed push
There needs to be a rapid progress made in less than 2 days, before the next hard fork working group meeting on 21st May (which is also a preprod epoch boundary)
That is supposed to be the last possible date when the hard fork working group can recommend forking Cardano PreProd testnet (governance action ratification would be enacted on 21st and enacted 5 days later on 26th of May). The governance action submission date for mainnet would stay the same, 29th May.
The criteria is relatively simple, Ogmios PRs is raised and official
If there is no Ogmios PR raised before the next PreProd epoch boundary on 21st, hard fork is highly likely to be delayed by at least one epoch, possibly more (depends on the iterative development work being done on the PR itself)
Exchanges need Rosetta-Java (expected by the end of next week) to be ready in order to progress on readiness, and Rosetta-Java is dependent on Yaci Store which is expected to become ready by the end of this week
All exchanges have been contacted
Overall readiness steadily increases
More ecosystem tooling becomes ready each day
SPO adoption rate of the hard fork ready node 11.0.1 is growing and is now at 32% according to pooltool.io (more than 10% increase in the last 5 days). This sets it as the version with the biggest single share.
Cardano entities (IO, Cardano Foundation, Midnight, Emurgo and Intersect) have established comms weeklies on Monday and also agreed communication channels for better collaboration and propagation of van Rossem related comms
Risk log was updated with increased likelihood for
Community is not ready for the Hard Fork,Failure to Hard Fork in a Timely MannerandOgmios upgrade not readyrisks
Hard Fork Working Group communication channels
Discord —
#wg-hard-fork
Action items and next steps
Sam/Ramsay/Kevin/Bosko: Have a discussion with the IO developer teams in the release meeting later today to check whether anybody can pick up the remianing work on Ogmios PR and do it rapidly so PreProd hard fork governance action can be ratified on 21st and enacted on 26th. That allows the possibility of still submitting mainnet hard fork governance action on 29th
Sam: Inform IO execs of the potential hard fork delay
Bosko: Inform Intersect execs of the potential hard fork delay
Bosko/Sam/Kevin: Make sure Ogmios is added to the critical tooling list
Bosko: Have an initial call with IO and Intersect people on drafted van Rossem support RACI matrix